You may be still hesitating about if you should purchase CCM braindumps pdf or CCM exam cram. You have no 100% confidence that you can pass exam yourself. So I want to ask you why you attend the CCM real test. If you just want to improve your skills and study more knowledge about Certified Case Manager Certification Exam (CCM) I will advise you to prepare yourself and don't care about pass score. If you really want to pass exam for Medical Professional CCM certification I will advise you to purchase CCM braindumps pdf or CCM exam cram.
Our CCM braindumps pdf guarantee candidates pass exam 100% for sure. Sometimes people say that our content material of our exam cram is nearly same with CCM real test. Normally we say that our CCM braindumps pdf includes 80% questions and answers of Medical Professional real test. If you aim to pass exam, We BriandumpsIT will be your best choice. So far more than 100000+ candidates all over the world pass exam with the help of our CCM braindumps pdf. Our passing rate for CCM is high up to 99.27% based on past data. All braindumps pdf is latest, valid and exact. Our professional and experienced education experts keep the exam cram material high-quality and easy to study. We are proud of our CCM braindumps pdf with high pass rate and good reputation.
Except of good material of CCM braindumps pdf our success is inseparable from our gold customer service. We build long-term cooperation with a large quantity of companies owing to our best customer service.
Before you buy we provide you the free demo for your reference. If you still have questions about Medical Professional CCM braindumps pdf, you can contact with us. Our customer service representative is 7*24 on-line (including all official holidays). We reply all questions and advise about CCM braindumps pdf in two hours. If you do not know how to choose PDF version, Software version and on-line APP version we will advise you based on your study habit. It is our pleasure to serve for you. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
After you pay we will send you the CCM braindumps pdf download link and password immediately, we are also on duty in holidays. If you have problems about downloading or some functions about Software version and on-line APP version of exam cram we are pleased to solve with you.
After you pass CCM if you do not want to receive our next update CCM - Certified Case Manager Certification Exam (CCM) braindumps pdf please tell us. Or our system will send you the update braindumps pdf automatically once it updates within one year service warranty. If you want to purchase other exam cram from us we will give you discount. We would like to build long-term cooperation with the company representative about CCM braindumps pdf.
We guarantee all people can pass exam if you pay attention on our Medical Professional CCM braindumps pdf. But just in case someone fails the exam, we guarantee we will refund unconditionally in 3 days after you send the unqualified exam score to us. We have confidence in our CCM (Certified Case Manager Certification Exam (CCM)) braindumps pdf. Our watchword is "Customer First, Service foremost" and "No Helpful, Full Refund".
Medical Professional CCM Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Rehabilitation Concepts and Strategies | 9% | - Worker recovery and return-to-work solutions - Vocational and physical rehabilitation pathways
|
| Ethical, Legal, and Practice Standards | 15% | - CCMC Code of Professional Conduct parameters - Regulatory compliance requirements and frameworks
|
| Quality and Outcomes Evaluation and Measurements | 18% | - Quality indicator metrics and performance tools
|
| Psychosocial Concepts and Support Systems | 27% | - Client dynamics and social determinants of health
|
| Care Delivery and Reimbursement Methods | 31% | - Case management concepts, processes, and principles - Reimbursement pathways and utilization management tools
|
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub- Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.
The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.
The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to
10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.
As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your " Notice of the Engineer ' s determination " , what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?
A) The Employer is not entitled to deduct the amount directly paid.
B) The Employer is entitled to deduct the amount directly paid.
2. Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?
A) The sequence and timing of the remedial work.
B) The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.
C) All key delivery dates of Plant and Materials.
D) The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).
3. Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
A) In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.
B) If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub- Clause 21.4 to obtain a DAAB decision on it.
C) Both ' Disagreement ' and ' Dispute ' are defined terms under the Conditions of Contract.
D) The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.
4. (Which two of the following statements are correct regarding types of Claims under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
A) The time bar only applies to Contractor's Claims and not to Employer's Claims.
B) The limit in time referred to in Sub-Clause 20.2.1 (also known as time bar) applies to all types of Claims.
C) If a Claim is submitted as per sub-paragraph (c) of Sub-Clause 20.1, this is dealt with by the Engineer or Employer's Representative (in case of FIDIC Silver Book) as per Sub-Clause 3.7/3.5.
D) If a Claim is submitted as per sub-paragraphs (a) or (b) of Sub-Clause 20.1, it is dealt with in accordance with Sub-Clause 20.2, which specifically covers claims for time and/or money. Part of the procedure under Sub-Clause 20.2 is for a payment and/or an extension of time-related claim to be agreed or determined by the Engineer/Employer's Representative (in case of the FIDIC Silver Book) in accordance with Sub-Clause 3.7/3.5.
5. (Under FIDIC Red and Yellow Books (both editions) the Engineer must have received technical education. Is this statement true or false?)
A) True
B) False
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: B,C | Question # 3 Answer: A,B | Question # 4 Answer: B,D | Question # 5 Answer: B |