NEW QUESTION 22
For which of these delays should an owner grant a time extension?
- A. Shop drawings and centrifuge delay.
- B. Structural steel shop drawings.
- C. Differing site conditions and centrifuge delay.
- D. Differing site conditions at parking structure.
Answer: D
NEW QUESTION 23
At a minimum, periodic reporting must be done at what interval?
- A. Monthly.
- B. As requested by the project manager.
- C. As requested by the owner.
- D. As specified in the contract documents.
Answer: D
NEW QUESTION 24
Time-scaled logic diagrams are
- A. Logic networks that are drawn to match the calendar.
- B. Only calculated using a computer.
- C. The same as a pure-logic diagram.
- D. Used to calculate the most probable activity duration.
Answer: A
NEW QUESTION 25
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.
- A. Estimate at completion (EAC)
- B. Budgeted cost of work scheduled (BCWS)
- C. Budget at completion (BAC)
- D. Budgeted cost of work performed (BCWP)
Answer: C
NEW QUESTION 26
In its simplest form, what is the main drawback of critical path method scheduling?
- A. It assumes that resources are unlimited.
- B. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
- C. It requires a backward pass to calculate late dates.
- D. It doesn't account for interdependent between activities.
Answer: A
NEW QUESTION 27
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
- A. 3.9% (1 : 25.708)
- B. 2.3% (1 : 43.501).
- C. 8.6% (1 : 11.591)
- D. 9.1% (1 : 11.000).
Answer: B
NEW QUESTION 28
Determine the correct formula and date for the late finish for Activity 2001.
- A. LF.2001 - 1 day -> 08-28-01.
- B. LS.2002 - 1 day -> 08-28-01.
- C. LS.2002- 1 day-> 08-29-01.
- D. LS.2002 + 1 day -> 08-30-01.
Answer: B
NEW QUESTION 29
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
- A. Project objectives in terms of cost, schedule and quality measures
- B. Project contract between the contractor and owner
- C. Project deliverables
- D. Project justification
Answer: D
NEW QUESTION 30
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?
- A. Project variables.
- B. Interest rate of owner's construction bonds.
- C. Consideration of all stakeholders.
- D. Value engineering.
Answer: B
NEW QUESTION 31
What owner action could have mitigated the late completion of the project?
- A. Hire a more senior project manager.
- B. Use a procurement agent to monitor and expedite equipment deliveries.
- C. Self-perform more of the work.
- D. Prepare better structural steel drawings.
Answer: B
NEW QUESTION 32
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
- A. 10 days.
- B. 0 days.
- C. 5 days.
- D. 15 days.
Answer: B
NEW QUESTION 33
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
- A. Front end loading.
- B. Preferential logic.
- C. Multiple calendars.
- D. Start and finish constraints.
Answer: A
NEW QUESTION 34
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.
- A. Estimate to complete (ETC)
- B. Estimate at completion (EAC)
- C. Budget at completion (BAC)
- D. Budgeted cost of work performed (BCWP)
Answer: A
NEW QUESTION 35
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
- A. Use gross building square footages. The pluses and minuses all average out.
- B. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
- C. Use the people responsible for performing the work as a resource to assign activity durations.
- D. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
Answer: A
NEW QUESTION 36
Which of the following phases does NOT describe the commonly accepted construction life cycle?
- A. Claims and disputes phase.
- B. Planning and design phase.
- C. Installation phase.
- D. Turnover and start-up phase.
Answer: B
NEW QUESTION 37
What is the cycle time?
- A. 14 minutes
- B. 5 minutes
- C. 6 minutes
- D. 17 minutes
Answer: D
NEW QUESTION 38
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
- A. 150 lifts
- B. 45 lifts
- C. 450 lifts
- D. 300 lifts
Answer: C
NEW QUESTION 39
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
- A. Production output.
- B. Acceleration.
- C. Productivity loss.
- D. Productivity efficiency.
Answer: C
NEW QUESTION 40
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
- A. 10 days.
- B. 5 days.
- C. 0 days.
- D. 15 days.
Answer: B
NEW QUESTION 41
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
- A. The delay must affect the contractor's planned construction schedule.
- B. The delay must not cause monetary harm to the defendant.
- C. The delay must affect the critical path.
- D. The delay must be concurrent with the delay attributable to both parties.
Answer: C
NEW QUESTION 42
What does the narrow band at "Y" represent?
- A. A rework period.
- B. You cannot tell with the information supplied.
- C. Resource limitation period.
- D. Activity inactivity.
Answer: D
NEW QUESTION 43
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
- A. Not suitable for projects with long durations.
- B. Not suitable for complicated projects with multiple planned critical paths.
- C. Less accurate as the analysis advances through the project.
- D. Accuracy is increased by inserting delaying events into the as-planned schedule.
Answer: D
NEW QUESTION 44
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
- A. ADM is limited to finish-to-start logic relationships, while PDM is not.
- B. PDM is a bar chart with network logic, while ADM is a pure logic network.
- C. ADM uses arrows, while PDM uses boxes.
- D. ADM is manual CPM calculations, while PDM is computerized.
Answer: A
NEW QUESTION 45
What is a key first step in developing a critical path method schedule?
- A. Setting out the resource to be used and its limitations.
- B. Drawing a bar chart of the key phrases of the work.
- C. Drawing the logic diagram.
- D. Defining the execution plan to meet the required scope of work.
Answer: C
NEW QUESTION 46
......
What is the duration, language, and format of the Planning & Scheduling Professional (PSP) Exam
- Total questions: 119
- Passing score: 70%
- Format: Multiple choice, compound, scenario questions + 1 memo writing assignment
- Language of Exam: English
- Duration of Exam: 5 hours