NEW QUESTION 22
For which of these delays should an owner grant a time extension?

  • A. Shop drawings and centrifuge delay.
  • B. Structural steel shop drawings.
  • C. Differing site conditions and centrifuge delay.
  • D. Differing site conditions at parking structure.

Answer: D

 

NEW QUESTION 23
At a minimum, periodic reporting must be done at what interval?

  • A. Monthly.
  • B. As requested by the project manager.
  • C. As requested by the owner.
  • D. As specified in the contract documents.

Answer: D

 

NEW QUESTION 24
Time-scaled logic diagrams are

  • A. Logic networks that are drawn to match the calendar.
  • B. Only calculated using a computer.
  • C. The same as a pure-logic diagram.
  • D. Used to calculate the most probable activity duration.

Answer: A

 

NEW QUESTION 25
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

  • A. Estimate at completion (EAC)
  • B. Budgeted cost of work scheduled (BCWS)
  • C. Budget at completion (BAC)
  • D. Budgeted cost of work performed (BCWP)

Answer: C

 

NEW QUESTION 26
In its simplest form, what is the main drawback of critical path method scheduling?

  • A. It assumes that resources are unlimited.
  • B. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
  • C. It requires a backward pass to calculate late dates.
  • D. It doesn't account for interdependent between activities.

Answer: A

 

NEW QUESTION 27
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

  • A. 3.9% (1 : 25.708)
  • B. 2.3% (1 : 43.501).
  • C. 8.6% (1 : 11.591)
  • D. 9.1% (1 : 11.000).

Answer: B

 

NEW QUESTION 28
Determine the correct formula and date for the late finish for Activity 2001.

  • A. LF.2001 - 1 day -> 08-28-01.
  • B. LS.2002 - 1 day -> 08-28-01.
  • C. LS.2002- 1 day-> 08-29-01.
  • D. LS.2002 + 1 day -> 08-30-01.

Answer: B

 

NEW QUESTION 29
Which of the following are NOT normally included in the project scope statement, either directly or by reference?

  • A. Project objectives in terms of cost, schedule and quality measures
  • B. Project contract between the contractor and owner
  • C. Project deliverables
  • D. Project justification

Answer: D

 

NEW QUESTION 30
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

  • A. Project variables.
  • B. Interest rate of owner's construction bonds.
  • C. Consideration of all stakeholders.
  • D. Value engineering.

Answer: B

 

NEW QUESTION 31
What owner action could have mitigated the late completion of the project?

  • A. Hire a more senior project manager.
  • B. Use a procurement agent to monitor and expedite equipment deliveries.
  • C. Self-perform more of the work.
  • D. Prepare better structural steel drawings.

Answer: B

 

NEW QUESTION 32
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

  • A. 10 days.
  • B. 0 days.
  • C. 5 days.
  • D. 15 days.

Answer: B

 

NEW QUESTION 33
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  • A. Front end loading.
  • B. Preferential logic.
  • C. Multiple calendars.
  • D. Start and finish constraints.

Answer: A

 

NEW QUESTION 34
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

  • A. Estimate to complete (ETC)
  • B. Estimate at completion (EAC)
  • C. Budget at completion (BAC)
  • D. Budgeted cost of work performed (BCWP)

Answer: A

 

NEW QUESTION 35
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

  • A. Use gross building square footages. The pluses and minuses all average out.
  • B. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
  • C. Use the people responsible for performing the work as a resource to assign activity durations.
  • D. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

Answer: A

 

NEW QUESTION 36
Which of the following phases does NOT describe the commonly accepted construction life cycle?

  • A. Claims and disputes phase.
  • B. Planning and design phase.
  • C. Installation phase.
  • D. Turnover and start-up phase.

Answer: B

 

NEW QUESTION 37
What is the cycle time?

  • A. 14 minutes
  • B. 5 minutes
  • C. 6 minutes
  • D. 17 minutes

Answer: D

 

NEW QUESTION 38
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

  • A. 150 lifts
  • B. 45 lifts
  • C. 450 lifts
  • D. 300 lifts

Answer: C

 

NEW QUESTION 39
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

  • A. Production output.
  • B. Acceleration.
  • C. Productivity loss.
  • D. Productivity efficiency.

Answer: C

 

NEW QUESTION 40
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 10 days.
  • B. 5 days.
  • C. 0 days.
  • D. 15 days.

Answer: B

 

NEW QUESTION 41
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

  • A. The delay must affect the contractor's planned construction schedule.
  • B. The delay must not cause monetary harm to the defendant.
  • C. The delay must affect the critical path.
  • D. The delay must be concurrent with the delay attributable to both parties.

Answer: C

 

NEW QUESTION 42
What does the narrow band at "Y" represent?

  • A. A rework period.
  • B. You cannot tell with the information supplied.
  • C. Resource limitation period.
  • D. Activity inactivity.

Answer: D

 

NEW QUESTION 43
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

  • A. Not suitable for projects with long durations.
  • B. Not suitable for complicated projects with multiple planned critical paths.
  • C. Less accurate as the analysis advances through the project.
  • D. Accuracy is increased by inserting delaying events into the as-planned schedule.

Answer: D

 

NEW QUESTION 44
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

  • A. ADM is limited to finish-to-start logic relationships, while PDM is not.
  • B. PDM is a bar chart with network logic, while ADM is a pure logic network.
  • C. ADM uses arrows, while PDM uses boxes.
  • D. ADM is manual CPM calculations, while PDM is computerized.

Answer: A

 

NEW QUESTION 45
What is a key first step in developing a critical path method schedule?

  • A. Setting out the resource to be used and its limitations.
  • B. Drawing a bar chart of the key phrases of the work.
  • C. Drawing the logic diagram.
  • D. Defining the execution plan to meet the required scope of work.

Answer: C

 

NEW QUESTION 46
......


What is the duration, language, and format of the Planning & Scheduling Professional (PSP) Exam

  • Total questions: 119
  • Passing score: 70%
  • Format: Multiple choice, compound, scenario questions + 1 memo writing assignment
  • Language of Exam: English
  • Duration of Exam: 5 hours

 