Try Before You Buy

Download a free sample of any of our exam questions and answers

  • 24/7 customer support, Secure shopping site
  • Free One year updates to match real exam scenarios
  • If you failed your exam after buying our products we will refund the full amount back to you.

Best Preparations of C_TS412_1909 Exam 2021 SAP Certified Application Associate Unlimited 82 Questions [Q27-Q45]

Share

Best Preparations of C_TS412_1909 Exam 2021 SAP Certified Application Associate Unlimited 82 Questions

Focus on C_TS412_1909 All-in-One Exam Guide For Quick Preparation.

NEW QUESTION 27
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.

  • A. Shift activities backward or forward on the time axis where more capacities are available.
  • B. Maintain subordinate internal activity elements assigned to other work centers.
  • C. Increase the capacities of the work center in the project planning board.
  • D. Trigger automatic capacity leveling inside the project planning board.

Answer: A,D

 

NEW QUESTION 28
What could be a reason to use expert mode in the valuation method for results analysis?

  • A. Assignments of different accounts for postings to financial accounting
  • B. Usage of different line IDs
  • C. Billing WBS elements belonging to different company codes
  • D. Valuation in different currencies

Answer: A

 

NEW QUESTION 29
To which object can you assign a factory calendar?

  • A. Milestone
  • B. Relationship
  • C. Network header
  • D. Material component

Answer: C

 

NEW QUESTION 30
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Milestones
  • B. Project definition
  • C. Sales order items
  • D. WBS elements

Answer: C,D

 

NEW QUESTION 31
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.

  • A. By searching via status combination code
  • B. By searching for the individual status
  • C. By searching via status selection profile
  • D. By searching for the status profile

Answer: B,D

 

NEW QUESTION 32
Where do you maintain the length of the project ID?

  • A. Project coding mask
  • B. Special characters
  • C. Project type
  • D. Project profile

Answer: A

 

NEW QUESTION 33
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?

  • A. Top-down
  • B. Bottom-up
  • C. Strict bottom-up
  • D. Free planning

Answer: B

 

NEW QUESTION 34
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. Structure overview
  • B. None
  • C. Extended capacity evaluation
  • D. Individual overview capacity requirements
  • E. Capacity load work center view

Answer: D

 

NEW QUESTION 35
What are some of the possible functions in user status profiles? Note: There are 2 correct Answers to this question.

  • A. Ensure user status must always be set manually.
  • B. Restrict setting user status for individual users.
  • C. Allow business processes forbidden by SAP system status.
  • D. Utilize priorities for setting the user status.

Answer: B,D

 

NEW QUESTION 36
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.

  • A. Production version
  • B. Material
  • C. Resource
  • D. Location

Answer: C,D

 

NEW QUESTION 37
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

  • A. The person responsible for the work center
  • B. The person responsible for the superior WBS element
  • C. The MRP controller for the network
  • D. The person responsible for the network activity

Answer: C

 

NEW QUESTION 38
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.

  • A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
  • B. You can only maintain the actual start of a WBS element if the finish date is not maintained.
  • C. You can always maintain the actual start and finish date of a WBS element.
  • D. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".

Answer: A,D

 

NEW QUESTION 39
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.

  • A. Automatic activation with the first actual posting
  • B. Automatic activation with budget assignment
  • C. Background activation (CJBV - Activate Availability Control)
  • D. Automatic activation with assignment to an investment program

Answer: B,C

 

NEW QUESTION 40
What functionality can you perform with activity elements?

  • A. Schedule WBS elements
  • B. Assign work centers and capacities
  • C. Assign material
  • D. Create relationships

Answer: D

 

NEW QUESTION 41
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.

  • A. A delivery document type must be configured.
  • B. A sold to party is necessary.
  • C. A sales order must be created in advance.
  • D. A shipping point is necessary.

Answer: B,D

 

NEW QUESTION 42
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.

  • A. Internal orders
  • B. Purchase order items
  • C. Sales order items
  • D. Reservations

Answer: B,D

 

NEW QUESTION 43
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

  • A. Network profile
  • B. Network type
  • C. Project profile
  • D. Parameters for the network type

Answer: D

 

NEW QUESTION 44
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
  • B. Earliest dates and latest dates are scheduled by forward scheduling.
  • C. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.
  • D. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.

Answer: D

 

NEW QUESTION 45
......