
Updated Oct-2021 Test Engine to Practice Test for C-TS422-2020 Exam Questions and Answers!
SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Certification Sample Questions and Practice Exam
NEW QUESTION 36
In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?
- A. Picking list
- B. Transfer Order
- C. Kanban
- D. Backflushing
Answer: A
NEW QUESTION 37
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Work Center BOM
- B. Sales Order BOM
- C. Functional Location BOM
- D. Class BOM
Answer: B,C
NEW QUESTION 38
What is the purpose of collective orders?
- A. To manage production orders for an entirefinished product on multiple levels
- B. To post any component withdrawals single back flush with order confirmation
- C. To combine order management of co-products and by-products with the main product
- D. To post production costs ona cost collector instead of the production order
Answer: A
NEW QUESTION 39
Which SAP solutions can be used for forecast ng in Supply Chain Planning? Note: There are 2 correct answers to this question.
- A. Supply Chain Management (SCM)
- B. Material Requirements Planning (MRP)
- C. Capacity Requirements Planning (CRP)
- D. Integrated Business Planning (IBP)
Answer: A,D
NEW QUESTION 40
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers tothis question.
- A. Add the agreement to the source list and mark itfor MRP relevance.
- B. Add the agreement to the quota arrangement and mark it for MRP relevance.
- C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
- D. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
Answer: A,C
NEW QUESTION 41
Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.
- A. In the production version
- B. In the production order type
- C. In the MRP controller
- D. In the routing
- E. In the bill of materials (BOM)
Answer: B,C,D
NEW QUESTION 42
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note:There are 2 correct answers to this question.
- A. In-house production time
- B. Total replenishment lead time
- C. Operation duration
- D. Planned delivery time
Answer: A,D
NEW QUESTION 43
In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.
- A. Fixed pegging (on/off)
- B. Finiteness level (0...1)
- C. Planning mode (bucket/sequence)
- D. Direction (forward/backward)
- E. Scheduling control (finite/infinite)
Answer: C,D,E
NEW QUESTION 44
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
- A. Specify a positive planning horizon in the strategy profile.
- B. Specify a negative planning horizon in the strategy profile.
- C. Specify a negative offset time in the strategy profile.
- D. Specify a positive offset time in the strategy profile.
Answer: C
NEW QUESTION 45
You are working with planning strategy 40 (Planning-with-final assembly). When does consumption of planned independent requirements take place?
- A. When the MRP results are saved
- B. When you create a sales order
- C. When you create a planned order
- D. When you deliver a sales order
Answer: B
NEW QUESTION 46
Where do you maintain the duration of a producton operation?
- A. Material master
- B. Routing
- C. Bill of material (BOM)
- D. Work instructions
Answer: B
NEW QUESTION 47
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
- A. Adjust the available capacity.
- B. Reduce the planning window.
- C. Select an alternative mode on a resource.
- D. Form optimum sequences to reduce setup times.
- E. Execute a new production planning run.
Answer: A,C,D
NEW QUESTION 48
What does the industry sector determine? Note: There are 2 correct answers to this question.
- A. Whether a material master fieldis required, changeable, displayed, or hidden
- B. Which material master views can be maintained
- C. Whether material numbers are assigned internally or externally
- D. Which transaction you can use to create a new material
Answer: A,B
NEW QUESTION 49
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.
- A. To reduce the number of material masters
- B. Tosimplify the structure of bills of material
- C. To reduce the number of changes required in bills of material
- D. To increase the number of planning levels
- E. To make the assignment of components easier
Answer: B,C,E
NEW QUESTION 50
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Control cycle
- B. Production supply area
- C. Rate routing
- D. Replenishment strategy
Answer: A
NEW QUESTION 51
What is the difference between co-products and by-products?
- A. Only co-products appear in the processor production order settlement rule.
- B. Only co-products are identified by a special item category in the bill of material (BOM).
- C. Only by-products have a zero inventory valuation.
- D. Onlyco-products can be manufactured in isolation from the main product.
Answer: A
NEW QUESTION 52
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP"/OS)?
- A. Use a propagation range.
- B. Use a planning group.
- C. Use a heuristic.
- D. Use a resource group.
Answer: C
NEW QUESTION 53
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.
- A. Wait time
- B. Move time
- C. Float before production
- D. Pick/pack time
- E. Queue time
Answer: A,D,E
NEW QUESTION 54
How would you define pegging in the context of Advanced Planning?
- A. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
- B. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
- C. An evaluation that is ordered according to thebill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
- D. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
Answer: C
NEW QUESTION 55
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The planning strategy is infinite.
- B. The work center has several individual capacities.
- C. The Change Planning Direct on indicator is set.
- D. Alternative resources are fully occupied.
Answer: A,B
NEW QUESTION 56
You want to insert an operation at a certain time on a work center. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?
- A. The previously dispatched operation stays as is the new operation is insertedafter the dispatched operation.
- B. The new operation is inserted at the desired time the previously dispatched operation is moved backward.
- C. The previously dispatched operation stays assist the new operation is inserted before the dispatched operation.
- D. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
Answer: B
NEW QUESTION 57
Which actions does the system perform by default when you save aconfirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
- A. Posting of goods receipt for the product
- B. Posting of production costs to the production cost collector
- C. Archiving of documents for assembly scrap
- D. Material staging for next order in sequence
- E. Reduction of associated capacity requirements
Answer: A,B,E
NEW QUESTION 58
......
Certification dumps SAP Certified Application Associate C-TS422-2020 guides - 100% valid: https://www.braindumpsit.com/C-TS422-2020_real-exam.html